Milestones

All dates are indicative and remain subject to change
  • 2021 Q4

    First phase of community consultation to introduce ourselves and receive feedback on our early stage proposals to help identify and understand any local impacts
  • 2022 Q1

    Environmental Impact Assessment (EIA) Scoping Request submitted to the Planning Inspectorate
  • 2022 Q2

    Publication of our Statement of Community Consultation (SoCC) and ongoing development of our EIA
  • 2022 Q3

    Second phase of consultation with community and technical stakeholders, including sharing the findings of our Preliminary Environmental Information Report (PEIR)
  • 2022 Q4

    Submission of DCO application to the Planning Inspectorate for public examination
  • 2023

    DCO examination and decision
  • 2024

    Anticipated start of construction